Today was the day that the concrete was poured.  We got a pump truck, which takes the concrete from the concrete trucks and shoots in up and down through a pipe.  This way the guys can control where it's going and get it the far side of the house where the trucks can't get to.

 

We ended up with 11 concrete trucks delivering 106 yards (cubic yards of concrete).  The trucks came in all morning and the slab guys worked almost all day on it.  And here is the beautiful new slab.